Day14:
Nice day, but only 1.5 workers. Contractor wanted a progress
payment for "starting the siding." Told them to finish
current task like the porch and roof AND that they couldn't do siding
until the wall of windows and door are removed and new windows
installed. DUH! Not much visible progress today.
Day 15: Nice 70 degree day. Again not much
progress. Hurricane straps did appear on the framing. I suspect
the city inspections make them add them.
Sunday: While Kathy and I were walking around the yard,
we discovered that the brick wall adjacent to the construction had
suffered MAJOR damage. A fifty foot section of this 5 foot tall
wall had structural cracks, bowing and was leaning toward the sidewall
at much as 10 degrees. It is in serious danger of falling over and
perhaps injuring pedestrians. Contractor had been backing their
dump trucks up the wall to load the considerable demolition
debris. They had caused the damage. We also discovered a
tile on the porch the crew had broken. We emailed Phil Rea and
asked them to come out Monday morning to discuss the wall issue before
starting any new work.
Day 16: Les' brother came out. He disavowed any
responsibility for the wall damage. Later that afternoon, he
showed up again with Kenny Brown, who was the project manager of our
kitchen renovation in 2002. Again they were not taking any blame.
They said they would return on Tuesday with their insurance adjuster to
view the wall. So, what do you think THEIR insurance provided will
do. NOTHING. Their insurance adjuster (Kathy Miller,
Nationwide) called me for a chat, but said she had no plans to come out
the next day. Work on the porch has stopped.
Day 17: Kathy, the "nice cop", has taken over
our negotiations with Phil Rea. Tim, the recalcitrant on-site
project manager, has been replaced with Kenny. Kenny says they
will come out within 24 hours and shore up the leaning, broken
wall. They are exploring the cost to fix the wall which will
likely mean tearing down the bad section and rebuilding it. We had
Sidney Pierce, a masonry contractor, come out to give us an estimate for
the repair. Sidney did say that cleaning the old bricks and
reusing them will cost 2 to 3 times what new bricks would cost.
Kenny came out late in the day and added some bracing for the sagging
wall. Given that he used a single nail at all joints, I'm thinking
this is a very flimsy band aide. Kenny said he would get free to
work on our project next week and even admitted that they were now
thinking that MAYBE they were 5% at fault for the wall damage.
Small progress.
Days 18-22: No progress. Sidney Pearce, a masonry
contractor came out and gave us an estimate of $8046 to tear down
the damaged wall and rebuild it. OUCH!!!
Day 23: Framed in the door to the removed deck so they could
begin installing the bead board porch ceiling. They primed all the
bead boards and left them to dry. I was gone most of the day and
there seemed to be little progress in general. It was a nice 60 degree
day. Insurance adjuster called about 5:30 and asked for copies of
my wall photos and the Pearce estimate for repairs. Emailed 17
photos (Ah, the joys of digital cameras!) and FAXed the estimate.
Day 24: They put in the bead board porch ceiling and did some
trip work. Two guys working.
Day 25: Kenny came after lunch. Repaired the roof
over the front dormer. Replaced maybe 16 square feet of rotted
sheathing and got the tar paper back on. Will finish on Monday and
fortunately there is little chance of rain over the weekend.
Day 26: Roof patch done and most of the day spent on trimming
out the porch. All bead board done. Of course there is still
substantial work to be done replacing the windows in the dormer and
associated trim work both inside and out.
Day 27: Kenny worked half a day (or less) cutting shingles to
size. No other work done.
Day 28: Kenny put up some shingles between times doing some
framing work in support of the plumbers.
Day 29: Misty rain, but warm. Kenny showed up but decided he
would work on the roof brackets at home. He called me a bit later
saying he had left the pad with the dimensions on the porch. I
read him the numbers, not feeling very confident with the translation.
Days 30-31: Kenny still doing final trim on the porch. He
said it is taking far longer than he expected. Looking good.
Day 32: March 31. Porch construction done (except of
course for the new window wall in the dormer (where the door the the
deck used to be.) Windows are scheduled to be here on April 20.
Kenny will try to get the painter out to put a coat of primer on
it. House painting will happen much later.
. . . . . . . . .
Day 58: May 11, Exterior cornice trim over windows done
incorrectly, Kenny will redo. Interior wall has not been started
yet.